Knowledge centre · Upgrade

Upgrading a filling line from piston to servo rotor pump

Most upgrade projects are not about speed. They are about how much product is given away on every container, and how much of the shift is spent adjusting the machine instead of running it.

What typically changes

ItemPiston lineServo rotor pump line
Metering elementPiston + valve seatRotor pump + servo drive
Fill volume changeoverMechanical adjustment or part changeParameter change on the HMI
Particle toleranceLimitedHigh — no seat to bridge
CleaningDisassembly for solidsCIP-capable configuration
Accuracy controlManual trial and re-adjustmentServo correction, check-weigh feedback

What usually stays

  • Conveyor, capping, labelling and coding stations — normally reused.
  • Container handling and accumulation.
  • Utilities, guarding and line control architecture, subject to inspection.

A changeover is therefore usually a filling-station retrofit rather than a new line — which is why the payback calculation is dominated by material savings rather than by throughput.

Planning the changeover

  • Weigh current fill performance statistically before the change — a baseline is the only way to prove the gain.
  • Confirm container and cap dimensions on site; nozzle geometry is where retrofit projects most often lose accuracy.
  • Decide the cleaning regime and choose CIP-capable construction if the product requires it.
  • Plan a product-specific acceptance test: dose a defined number of consecutive fills and weigh them.